30 Nov 2000
Highland Pine Products Oberon Mill (NSW)
Construction
The sorter consisted of a 40 bin 140 boards per minute feed and sorting system, with the stacking system having a similar capacity. This project had a construction and commissioning period of less than 2 weeks.
The construction design was focussed on maximising pre work as well as off site works in order to minimise the shutdown installation time. The plant was constructed and commissioned on time to a budget of AUD$400k.