The Yimuyn Manjerr Mine (formerly the Mt Todd Gold Mine), located some 50km
North of Katherine, NT, was a 9MTpa Open Cut Mine and process plant.
The new owners made major processing modifications to the plant. RJE's
responsibility was to re-design the plant Electrical, Instrumentation
and Control System to incorporate the modified process design. In addition
to the design works, RJE completed the associated construction works,
re-commissioned the plant and incorporated the modified control system.
The project was completed both on time and on budget at ~$400k